West Wits Mining ROM Ore Pad HDPE Geomembrane Lining - Supply, Installation & QA/QC
Supply, installation and documented QA/QC of GSE HDPE geomembrane lining with geotextile protection for ROM ore pads at West Wits Mining.
Project at a glance
- Application
- Mining containment
- Location
- South Africa
- System
- 1.5 mm GSE HDPE + protection geotextile
- Scope
- Supply, installation & documented QA/QC
Project: West Wits Mining - ROM Ore Pads
Location: South Africa
Completion Date: February 2026
Contractor: Geosynthetics South Africa Pty Ltd
Geosynthetics Africa was engaged to deliver a fully engineered geomembrane containment system for ROM ore pads, including supply, logistics, installation, and full QA/QC verification.
The project required a load-bearing, puncture-resistant containment solution capable of withstanding:
- Continuous heavy equipment traffic
- High static and dynamic ore loads
- Environmental exposure
- Strict containment compliance
ENGINEERED SYSTEM DESIGN
This was not a standard liner installation , it was a multi-layer engineered containment system designed for mining operations.
System Cross-Section (Bottom to Top)
| Layer | Specification | Function |
|---|---|---|
| Subgrade | Compacted G6 (95% Mod AASHTO) | Structural foundation |
| Bedding Layer | 50-100 mm selected sand | Smooth surface & liner protection |
| Containment Layer | GSE HDPE Geomembrane (1.5 mm) | Impermeable barrier |
| Protection Layer | MIRAFI S82 Nonwoven Geotextile | Puncture resistance |
| Working Layer | 100-150 mm selected material | Load distribution |
| Traffic Layer | 200-300 mm crushed material | Operational surface |
✔ Designed for high load mining environments
✔ Engineered to prevent puncture, deformation, and leakage
✔ Fully aligned with GRI-GM13 geomembrane standards
CRITICAL ENGINEERING FEATURES
1. Anchor Trench System
- 150 × 150 mm anchor trench on three sides
- Provides long-term liner restraint
- Prevents uplift and edge instability
2. Drainage Control System
- Perimeter drainage trench (lined)
- Controls runoff and prevents contamination migration
3. Concrete Hump Interface
Engineering Purpose:
- Controls surface water ingress
- Protects liner at high-risk entry zone
- Provides traffic transition from haul road to lined pad
- Acts as a termination and interface boundary
Geosynthetics Africa integrated the geomembrane system into this feature, ensuring:
- Controlled liner termination
- Protection against shear stress
- Long-term durability at the most critical interface
MATERIALS SUPPLIED & INSTALLED
Geomembrane
- Product: GSE HDPE Geomembrane
- Thickness: 1.5 mm (approved upgrade from 1.25 mm)
- Standard: GRI-GM13 compliant
- Manufacturer: GSE / Solmax
Geotextile Protection
- Product: MIRAFI S82 Nonwoven
- Function: Cushioning + puncture resistance + separation
TRACEABILITY & MATERIAL CONTROL
All materials were:
- Manufactured in ISO-certified facilities
- Fully batch traceable
- Delivered in original labelled rolls
- Verified against factory QA documentation
📌 Full traceability records maintained in QA system
INSTALLATION METHODOLOGY
- GSE Manufacturer Guidelines
- Group IAGI Installer Member: Geosynthetics Africa holds the membership, and Geosynthetics South Africa follows the group's installation and QA/QC procedures.
- Project-Specific Method Statements
Execution Sequence
1. Subgrade Preparation
- Inspection and approval of prepared surface
- Removal of sharp materials
- Placement of controlled sand bedding
2. Liner Deployment
- Panels installed along wind direction
- Minimum 100 mm overlaps
3. Welding Operations
- Dual-track hot wedge welding
- Extrusion welding for details and repairs
4. Protection Layer Installation
- MIRAFI S82 placed over liner
- Ensured full coverage prior to loading
5. Final Layer Placement
- Controlled placement of sand and crushed material
WELDING & QA/QC CONTROL
Equipment
- Leister Hot Wedge Welders
- Leister Extrusion Welders
- Vacuum Testing Units
- Air Pressure Testing Systems
Welding Procedure
- Six trial welds performed
- Optimal parameters selected (temperature, speed, pressure)
- Continuous monitoring and recalibration
📌 Trial weld optimisation confirmed before production
QUALITY ASSURANCE & TESTING
- Air Pressure Testing (double seam)
- Vacuum Box Testing
- Visual Inspection
- Trial Weld Testing
Acceptance Criteria
- Continuous weld integrity
- Zero leakage
- No voids or defects
Results
- 100% seam testing completed
- One localized defect repaired and retested
- Full system integrity confirmed
📌 Installation certified compliant post-testing
HEALTH, SAFETY & ENVIRONMENTAL PERFORMANCE
- Zero incidents recorded
- Full PPE compliance
- Controlled work zones
- Strict liner protection protocols
PROJECT OUTCOME
✔ Fully engineered containment system delivered
✔ Installation compliant with international standards
✔ Integrated civil + geosynthetic system executed successfully
✔ System approved for operational use
📌 Final sign-off confirms compliance with all specifications
STRATEGIC PROJECT SIGNIFICANCE
This project demonstrates Geosynthetics Africa’s capability to deliver:
1. Load-Bearing Mining Containment Systems
Not just liners - engineered operational platforms
2. Civil + Geosynthetic Integration
- Concrete interface (hump)
- Drainage systems
- Anchor trench systems
3. Full Lifecycle QA/QC
- Material traceability
- Installation QA
- Testing verification
Why choose Geosynthetics South Africa?
We are a specialist geosynthetics engineering contractor delivering:
- HDPE Geomembrane Systems (GSE / Solmax)
- Geotextile Protection Systems (MIRAFI)
- IAGI-Compliant Installation
- Pan-African Delivery Capability
Applications
- ROM Pads
- Heap Leach Pads
- Tailings Storage Facilities
- Water Containment Systems
Geosynthetics Africa delivers engineered containment systems - not just liners.
From material supply to final QA certification, we ensure:
✔ Structural performance
✔ Environmental compliance
✔ Long-term durability
Trusted by mines. Proven in the field. Built for Africa.